Custer Road Construction Update - LKW

This week, the curb has been poured. Excavation and preparation for street lighting bases continue.
The contractor is grading for the sidewalk and preparing the intersection at 75th and Custer for sidewalk retrofit.
Lakewood thanks the utility providers for their timely relocation efforts.
Gas, communications, and water relocations are all anticipated to be completed this week.